ARTSON ENGINEERING LIMITED
DESCRIPTION OF WORK |
YEAR |
Detailed Engineering done of Piping & Structural works for the project of HPCL Plant, at Mahul – FCCU UNIT. |
1997 |
TECHNIP KT INDIA LIMITED
DESCRIPTION OF WORK |
YEAR |
Detailed Engineering done of Piping work for the project of HPCL Plant, at Mahul – DHDS/ SRU UNIT. |
2000 |
AKER KVAERNER ENGINEERING S.E.A. SDN. BHD.
DESCRIPTION OF WORK |
YEAR |
Detailed Engineering done of Piping, Structural & Electricals works for the project of Reliance Industries Ltd. (K4D-6). |
2006 |
Detailed Engineering done of Piping, Structural & Electricals works for the project of Bunja Orkid (Bo-A) Central Process Platform of Talsiman Malaysian Ltd. |
2006 |
RELIANCE INDUSTRIES LIMITED
DESCRIPTION OF WORK |
YEAR |
Detailed Engineering done of Piping, Structural & Electricals works for the project of Jamnagar Refinery – Phase I & Phase II |
2006 - 2007 |
TOYO ENGINEERING INDIA LIMITED
DESCRIPTION OF WORK |
YEAR |
Detailed Engineering done of Piping for offsites & utilities area of Chambal Fertilizer & Chemical Limited |
1992 |
LARSEN & TOUBRO LIMITED. (ECC GROUP )
DESCRIPTION OF WORK |
YEAR |
Detailed Engineering done of Piping for Sponge Iron / Hot Mills / Cold Mills & Blast Furnace Plant at Ispat Industries Ltd. |
1995 |
UHDE INDIA LIMITED
DESCRIPTION OF WORK |
YEAR |
Detailed Engineering done of Piping for offsites & utilities area of Gujarat State Fertilizer & Co. Ltd. |
1992 |
Detailed Engineering done of Piping, Structural & Electrical works for Mangalore Refineries Petrochem Limited |
1993 |
JOHN BROWN TECHNOLOGIES (L) PVT. LIMITED
DESCRIPTION OF WORK |
YEAR |
Detailed Engineering done of Piping, Structural & Electricals works for the project of Vasai East – BCPA – Process Platform for ONGC Ltd. |
2004-2005 |
Detailed Engineering done of Piping, Structural & Electricals works for the project of Mumbai Heera Fields – 4 Well Head Project (MH & BS) for ONGC Ltd. |
2006 |
Detailed Engineering done of Piping, Structural & Electricals works for the project of Dubai High Fields N-9/N-10 Well Head Platform for ONGC Ltd. |
2003 |
Detailed Engineering done of Piping & Structural works for the project of HDS Reactor II of HPCL Refinery Project. |
2001-2002 |
Detailed Engineering done of Piping & Structural works for the project of Panna Field Development & Modification Project for BG India Ltd. |
2005 |
Detailed Engineering done of Piping, Structural & Electrical works for the project of LA & LB Platform Project for Gulf of Cambay of ONGC Ltd. |
2005 |
Detailed Engineering done of Piping, Structural & Electrical works for the project QPS Living Quarter & Power up gradation for PS-2 / PS-3 for Qatar Petroleum. |
2004 |